Benbrook drivers may want to plan a different route beginning Wednesday, November 11, as the city prepares to resurface portions of Sproles Drive and Vernon Castle Avenue.
The work is part of Benbrook’s 2027 Asphalt Overlay Program and is expected to take approximately two weeks, with completion anticipated around November 25, weather permitting.
According to the city, Texas Materials will oversee the roadway improvements, which may cause temporary traffic delays, lane restrictions, and limited street parking in affected neighborhoods.
Residents should be aware of parking restrictions from 7 a.m. to 4 p.m., Monday through Friday, within designated work zones. Vehicles must be moved before 7 a.m. to allow construction crews to work safely. Normal parking may resume once daily work is completed and the roadway reopens.
Residents are encouraged to follow posted traffic signs, use caution near construction crews, and consider alternate routes during the project.
For project updates, visit Benbrook at a Glance. Questions may be directed to Heath Haseloff at hhaseloff@benbrook-tx.gov or Texas Materials Project Manager Angelica Torres at angelica.torres@texasmaterials.com.
Additional information is available through the City of Benbrook’s announcement.








Leave a Reply
You must be logged in to post a comment.